Question 21 of 207 · Medium
Questions and answers are free. Sign in optionally to save progress.
Oundle 2012Q16
(a)
It takes 4 hours for 1 person to build a fence.
How long would it take to build the fence if there were 2 people working on it? (Assume all people work at the same pace)
(b)
It takes 2 hours for 3 people to paint a wall.
How many people would be required to paint the wall in 1 hour?
(c)
It takes 4 hours for 3 people to dig a hole.
How many people would be required to dig the hole in 3 hours?